Tentative Project Schedule

Conduct Traffic and Transportation Study

Winter 2001
Begin Environmental Data Collection and Documentation Winter 2001
First Public Meeting May 2001
Preliminary Engineering Alternatives  Summer-Fall 2001
Detailed Alternatives Analysis Winter 2001
Second Public Meeting (for Detailed Alternatives Analysis) January 2002
Environmental Clearance

August 2006
Complete Preliminary Engineering

June 2007
Complete Final Design   March 2009
Start Construction   May 2009

  
(item is complete)